STEP 1 - Reservation Request Form
In this initial step the applicant can reserve MASH funds. The project does not have to be complete, or even started in order to secure a reservation. Upon successful submission of the following documents the Program Administrator will submit a reservation notice detailing the amount reserved.
All submission information can be found in the Reservation Request Form. Reservations are good for 18 Months.
-
Completed Reservation Request Form and Completed Contract with Original Signatures (See Forms Below)
-
Electrical System Sizing Documentation (If Applicable)
-
Documentation of CPUC Code 2852 Eligibility (Proof of Low-Income Status)
-
Documentation of an Energy Efficiency Audit or Title 24 Documentation or Other Exemption (see link to energy audit tools below).
-
Copy of Signed Energy Efficiency Disclosure Form (Beginiing July, 1 2009)
-
Printout of EPBB Tool Calculation (www.csi-epbb.com)
-
Completed Form "Authorization To: Receive Customer Information or Act on a Customer's Behalf"
Forms:
MASH Reservation Request Form (RRF) (114.5 kB)
Authorization To Receive Customer Information
MASH Energy Efficiency Disclosure Form (44.18 kB)
Links to residential and commercial energy audit tools on utility website:
Commercial Audit
Residential Audit
Links to third-party residential and commercial energy audit tools:
www.gosolarcalifornia.ca.gov
www.aceee.org
www.fypower.org
www.energystar.gov
| kW ≥ | < kW | FEE | ||
| 10 | - | 50 | = | $1,250 |
| 50 | - | 100 | = | $2,500 |
| 100 | - | 250 | = | $5,000 |
| 250 | - | 500 | = | $10,000 |
| 500 | - | 1,000 | = | $20,000 |
STEP 2 - Proof of Project Milestone
In this step the Program Administrator requires an additional set of documents that demonstrate the project is moving forward.
-
Completed Proof of Project Milestone Checklist
-
Copy of Executed Contract for System Purchase and Installation
-
Copy of Executed Alternative System Ownership Agreement (If System Owner is Different than Host Customer)
-
Revised EPBB Calculation Printout (If Applicable, www.csi-epbb.com)
-
Copy of Request for Proposal (RFP) or Solicitation (If Applicable)
Forms
PPM - Proof of Project Milestone (56.5 kB)
STEP 3 - Incentive Claim Form
The following documentation must be submitted after the solar system is installed and interconnected.
-
Completed Incentive Claim Form with Original Signatures
-
Copy of Executed PMRS Contract or PMRS Cost Cap Exemption Documentation
-
Revised EPBB Calculation Printout (if Applicable)
- Completed Field Verification Form
Forms
MASH Incentive Claim Form (ICF) (120.5 kB 2010-03-05 17:27:36)
Field Verification Form (42.5 kB 2010-06-08 09:16:56)





