Application Requirements

The SGIP 2013 Program Year is now open! Please refer to the 2013 Program Handbook and use the new forms when submitting your application. Program forms from previous years will not be accepted.

For all residential projects and small (<10kW) nonresidential projects, a two-step application process is available. Large (≥10kW) nonresidential projects usually follow a three-step application process but may chose a two-step application process if they are able to meet all two-step requirements.

 

2 Step Application Process

3 Step Application Process

For the three-step process, the application requirements and timelines vary somewhat between public and nonpublic entities.  The following table describes the application timelines and due dates for the different application processes. For a more detailed description of the application process, please visit the icon Application Process Overview.

Application Process Timelines


2-Step

3-Step (Non-Public)

3-Step (Public)

Eligibility

All residential projects
Nonresidential projects < 10kW

Nonresidential projects ≥10kW
Nonpublic entities

Nonresidential projects ≥10kW
Public entities

STEP 1

Reservation Request
Project receives Reservation Confirmation (RC)

Reservation Request
Project receives Conditional Reservation ( CR)

Reservation Request
Project receives Conditional Reservation ( CR)

STEP 2

NA

NA

Request for Proposal
Due 60 days from date of CR

STEP 3

NA

Proof of Project Milestone (PPM)
Project receives Reservation Confirmation
Due 60 days from date of CR

Proof of Project Milestone (PPM)
Project receives Reservation Confirmation
Due 240 days from date of CR

STEP 4

Incentive Claim
Project receives Final Approval
Due 12 months from date of RC

Incentive Claim
Project receives Final Approval
Due 18 months from date of CR

Incentive Claim
Project receives Final Approval
Due 18 months from date of CR

SGIP funds are available on a first-come, first-served basis throughout the calendar year (January 1 - December 31). Reservations received after total funds have been committed for a calendar year will be placed on a wait list. A place on the wait list is not secured until the Program Administrator receives all information and documentation required with the Reservation Request Form and the project is determined to meet all eligibility requirements.

 