Sunrise Powerlink Transmission Project (A.06-08-010)
San Diego Gas & Electric ( SDG&E) seeks authority from the California Public Utilities Commission ( CPUC) to construct a 500 kV transmission line in conjunction with several 230 kV transmission lines, expected to run 150 miles between the Imperial Valley to San Diego.
What's new:
On April 16, SDG&E filed its Thirteenth Quarterly Project Status Report, as required by Ordering Paragraph 13 of D.08-12-058, which granted a certificate of public convenience and necessity for the Sunrise Powerlink Transmission Project. In the report, SDG&E provided their project status update, answering eight required questions regarding the status of the project. SDG&E notes that significant construction progress was made during the first quarter of 2012, with construction of the overhead portion of the project now approximately 75% complete. In addition, SDG&E indicates that the Suncrest substation construction is approximately 98% complete, with only minor wiring, site grading and testing yet to be completed, and construction of the underground transmission line is now complete with testing under way.
| < Prev |
|---|









